Trump Greenlights Keystone and Dakota Access Pipelines, but the Battle is Far From Over

$
0
0

President Trump wasted no time making good on his promise to reverse President Obama’s efforts to reduce greenhouse gas emissions and move U.S. energy policy towards cleaner energy sources.  On January 24 Trump signed two executive memoranda, one inviting TransCanada to resubmit its application to build the 800,000 barrel a day Keystone XL pipeline from the Canadian oil sands to the Gulf Coast; the other directing the Army Corps of Engineers to expedite the review and approval of the Dakota Access Pipeline (DAPL) to carry approximately 500,000 barrels per day of crude oil from the Bakken shale in North Dakota to oil markets in the United States. But a close reading raises some sticky legal and economic issues that will have to be resolved before the oil starts flowing.  [LINKS to Keystone and DAPL Memos]

In announcing the Keystone Memo, Trump said that approval was contingent on TransCanada’s  willingness to “renegotiate some of the terms” – including perhaps a commitment to use US steel and a share in any profits. The problem is that tar sands oil is not only the dirtiest fuel on the planet, it’s also the most expensive to extract. To be profitable oil prices need to be above $80 per barrel; today they sit around $52, and it is unlikely they will rise much higher in the foreseeable future given the competition from shale oil and the fracking boom that is flooding the market in the US. The break-even point for Bakken shale oil is $29 per barrel. Seventeen major oil sands projects were canceled after oil prices crashed in 2014, as companies took major losses. Major investors in the oil sands have begun to leave, including Norway-based Statoil, which pulled out of the oil sands in December 2016. So cutting a deal to the President’s liking may be harder than it looks.

Assuming the deal goes down, the Keystone Memo issues several directives to clear the way for the project. It directs the State Department to make a final decision within 60 days of the date TransCanada re-submits its application, and it further specifies that “to the maximum extent permitted by law” the final supplemental EIS issued in 2014 shall satisfy the requirements of NEPA as well as the consultation requirements of the Endangered Species Act, and “any other provision of law that requires executive department consultation or review.” The Keystone Memo also directs the Corps of Engineers to use Nationwide Permit 12 to summarily authorize the stream crossings needed to complete the project. These fast track measures are sure to be tested in court by the opponents who are not about to let their hard won victory be snatched away without a furious fight—in the courts as well as in the streets. While courts have ruled that the presidential permit itself is not reviewable, there is presumably no bar to challenging the decisions of the Corps and the Department of Interior that are necessary to complete the project.

The DAPL Memo directs the Secretary of the Army and the Chief of the Corps of Engineers to “review and approve in an expedited manner, to the extent permitted by law and as warranted, and with such conditions as are necessary or appropriate, requests for approvals to construct and operate the DAPL, including easements or rights-of-way to cross Federal areas under section 28 of the Mineral Leasing Act.” The Memo also instructs the Secretary to consider whether to rescind the memorandum issued by the Obama administration requiring preparation of an EIS on DAPL’s   request for an easement to cross Lake Oahe, and to deem the previously-issued Environmental Assessment sufficient to satisfy NEPA.

The Standing Rock protest over DAPL has become an historic confrontation that has united an Indigenous land-and-water movement and climate activism to confront a fossil-fuel corporation protected by a militarized police force.  At one point in December thousands of veterans arrived to provide a safe space for the protesters who call themselves “water protectors.” Litigation filed by the Standing Rock Tribe and other tribes challenging the Corps’ issuance of permits under the Clean Water Act and Rivers and Harbors Act is pending in federal district court in the District of Columbia.  Judge Boasberg denied a preliminary injunction but has yet to rule on the merits of the case. At the moment, the court is considering DAPL’s motion for summary judgment to declare that the project already has all of the approvals it needs and the Corps should not be able to reverse its earlier decision that an EIS was not required. Though the Justice Department has vigorously opposed this move, it will be interesting to see whether the Trump administration adopts a different posture. In any event, the Tribe has raised serious questions about whether the Corps properly evaluated threats to its water supply intake and alternative routes that would lessen the risk. One of the allegations invokes environmental justice concerns arguing that the project was re-routed away from Bismarck in response to concerns about threats to its water supply. The Tribe has also raised novel questions about whether granting the easement would violate treaty rights under the 1851 Treaty of Fort Laramie.

At the hearing on DAPL’s motion for summary judgment, Judge Boasberg acknowledged the uncertainty about what the new administration might do but observed that “It’s not my business to guess.” For now the rest of us will have to guess at what the final outcome of this epic confrontation that has galvanized indigenous peoples from all over the world will be.